Satellite and drone images reveal big delays in US data center construction
Quick Insights
The Bottom Line
Nearly 40% of US data center projects face significant delays due to labor, power, and equipment shortages.
How This Affects You
Delays in data center construction could slow the growth of digital infrastructure and cloud services, potentially impacting your access to or cost of online services.
AI Summary
Satellite imagery analyzed by the Financial Times and SynMax reveals that nearly 40 percent of US data center projects may not be completed as scheduled this year. This analysis, which cross-checked progress against public statements and IIR Energy permit documents, indicates major projects from companies like Microsoft, Oracle, and OpenAI are "likely to miss completion dates by more than three months." The delays stem from "chronic shortages of labor, power and equipment," alongside difficulties in securing necessary permits. Construction executives involved with OpenAI projects specifically cited a lack of tradespeople, such as electricians and pipe fitters, as a significant challenge. These issues are hindering the massive buildout of AI data centers, which require substantial electricity and face growing local resistance.
Following this story?
Get notified when new coverage appears
This article is part of a story we're tracking:
Should this be getting more attention?
You Might Have Missed
Related stories from different sources and perspectives
TechnologyMaine passes first-in-nation freeze on big data centers
The Maine legislature passed the first state ban in the nation on the development of large data centers on Tuesday. The temporary measure, which lasts for 1.5 years, restricts the construction of new data centers that use over 20 megawatts of power. The bill now heads to the desk of Gov. Janet Mills (D) for…
CorporateTrump-branded AI data center megaproject stalls, CEO departs
<p>The world's largest data center project — backed by Trump allies and bearing his name — is stalled by delays and logistical hurdles that could stop it before it even starts.</p><ul><li>The latest sign of trouble emerged Friday: CEO Toby Neugebarger <a href="https://app.quotemedia.com/data/downloadFiling?webmasterId=102691&ref=319962036&type=HTML&cdn=e387f6899f29edcf08e78f3ef8ed1836&formType=8-K&formDescription=Current+report+pursuant+to+Section+13+or+15%28d%29&dateFiled=2026-04-17&cik=2071778" target="_blank">abruptly departed</a>. That sent the company's shares, which already shed 75% in the last six months, plummeting in aftermarket trading.</li></ul><hr><p><strong>Why it matters: </strong>Fermi America, co-founded by President Trump's former Energy Secretary Rick Perry, is emerging as a high-profile test of whether the biggest, most ambitious AI infrastructure projects can deliver on their promises.</p><p><strong>Behind the scenes: </strong>In an in...
National SecuritySatellite images reveal Israel expanding Gaza military sites
Images show Israel building permanent military bases in Gaza as US-backed reconstruction plans stall.
TechnologyThe data center boom meets resistance in Maine as lawmakers pass a yearlong freeze - AP News
<a href="https://news.google.com/rss/articles/CBMiuAFBVV95cUxQdVNuVTVNUnZ0aDFwN0ExUkRxWHlXMzAtSTA1TU5WM1g2ZWRJTU9OVGZ4UDRnVURuSlpkZkxiVnQyZDZtSnRtUXAycDFEOHNneHphTGM3YmdaR0NlaXZYZjh2WjYyVGUxVUZLdkZ0TkUwLTBSckNlYUxDTG1NejVtcUplckxaYXJkR1ZhRXg4cmd0cGk0bzdNVWpBT2NCX21yYmxwdms4ZzdHa1A4X0paSC1NbVYtNktu?oc=5" target="_blank">The data center boom meets resistance in Maine as lawmakers pass a yearlong freeze</a> <font color="#6f6f6f">AP News</font>
PoliticsMaine Said No to New Data Centers. Other States Are Racing to Follow.
The AI infrastructure reckoning has until recently stayed local, its battles fought in the relatively puny arenas of town council and zoning commission meetings. But the pushback to hyperscale data centers has now stepped onto a larger stage: this week, Maine’s legislature passed the nation’s first state-level hyperscale data center moratorium, freezing construction approvals for […]
PoliticsData centers are expensive, unpopular — and could be a tipping point in the midterms
Anger over the data center boom has spilled into politics with voters unseating local politicians who support them. It's become an issue hard to ignore in the midterm elections.

Florida Opens Criminal Inquiry Into ChatGPT Tied to Fatal School Shooting - The New York Times
Did this story change how you see things?
Stories like this only matter when people see them. Help us get verified journalism in front of more eyes.
The Verity Ledger curates verified investigative journalism from trusted sources only.
See our sourcesMost Read This Week
Report: Merck’s blockbuster cancer drug topped $200,000 a year under Trump

One in three Americans forced to make financial sacrifices for health coverage

Pope blasts ‘tyrants’ ravaging the Earth during his visit to Cameroon - AP News

Justice Jackson chides Supreme Court conservatives over 'oblivious' pro-Trump emergency orders - AP News

Leavitt discusses "Arc de Trump" at White House briefing